Avoiding Flood Season Delays on a Constrained Heritage Site 

Client: Developer 
Package: Structural Shell 
Building Systems: Timber Frame 
Type of Building: Development  
Energy Saving: Fabric First 

The Background 

This project carried two clear commercial exposures from the outset: 
 
Cost and performance certainty: planning required very high energy standards with little tolerance for post-approval change. 
 
Programme exposure to flood season: any delay to achieving weather-tight would have pushed the build into a known flood window, increasing cost, delay and insurance risk. 

Our Delivery Challenges 

Although the project was small in unit numbers, it was complex to deliver: 
 
Very tight site access at the end of an existing development 
Minimal laydown and lifting space 
Strict dimensional tolerances and heritage-style form  
Higher than standard U-value requirements. 
Developer team unfamiliar with timber frame, interface risk 

How we Removed Risk 

Several early decisions materially reduced downstream exposure: 
 
Digital design used to coordinate panel sizes, lifting strategy and delivery sequencing 
Sequenced manufacture and just-in-time deliveries to eliminate on-site storage 
Early co-ordination with the foundation contractor to control tolerances 
Pre-agreed installation methodology, including crew size, crane days and panel sequencing 

Outcome Certainty Gained 

Structure installed in 10 working days with a two-person team 
Three planned crane days, delivered without disruption 
Homes weather-tight ahead of flood season 
Performance targets achieved without redesign delays 
Reduced neighbour impact due to short site duration 
Heritage form and proportions matched exactly 
Ongoing support reduced risk for follow-on trades 
 
Critically, the client avoided the compounded cost and programme risk associated with seasonal delay. 

 Ready to discuss your project? 

Ready to discuss your project? 

 
 
 

Interested in more news and insight?